Day 101: April 26, 2011

I continued work on the kitchen drain (finished) and the bathroom drain. Mark worked on the living room drywall.

Mark reported dampness on the south living room wall, above the fireplace. It appears we have a leak in the flashing around the chimney. When the rain stops (IF the rain stops), we'll get up on the roof and take a look.

In the afternoon, Mark and I picked up the bathtub, which had been on special order from Menard's. I also placed orders for two basement windows.